Infrastructure Projects, Water Projects

Badr Villages Sewage Pump Stations

Ongoing Project

Customer

Behira Water And Drainage Company, BWADC

Project Status

Work in Process

Project Duration

24 months

Signage date

23/5/2019

Start Date

28/6//2019

Type

Water projects

Contract Value

20,432,301 EGP

SCOPE OF WORK

Engineering, Procurement, Installation for the plant  elements

for example not limited to:        

Supply and install submersible pumps, pipelines including all valves and joints, screens, cranes, control system, and all electronically works.