Energy Projects, Infrastructure Projects

New 6th October Substation 500/220/22 KV GIS Substation

Completed Project

Customer

Egyptian Electricity Transmission Company (EETC)

Role

Consortium (GE-Madkour)

Contract Type

Lump-Sum Price On EPC

Project Duration

12 Months

Project Status

in progress

Type

Transmission project-Substation

Year

2018

SCOPE OF WORK

Engineering, supply,  construction,  testing and commissioning.

     The system includes -not limited to-:         

    • 500, 220 & 22 KV Outdoor Equipment.
    • 500 &220 KV Gantries.
    • HVAC System
    • 220kV HV Cables.
    • 22 KV Switchgear.
    • AC/DC Auxiliary System.
    • Earthing System.
    • Fire Hydrant & Firefighting System.
    • MV-LV-Control Cables & Cable Trays.
    • Civil Works
    • Construction, testing and commissioning for whole Substation.