Energy Projects, Infrastructure Projects

Lina Farm 66/22 KV AIS Substation

Completed Project

CUSTOMER

EL Banna for agricultural

ROLE

Main Contractor

CONTRACT TYPE

EPC

PROJECT STATUS

Completed

PROJECT DURATION

1 Year

type

Transmission Projects- Substation-MN

value

110,000,000 EGP

year

2018

SCOPE OF WORK

Engineering, supply,  construction,  testing and commissioning.

The system includes -not limited to-:         

    • 66 KV AIS.
    • 66/22 KV, 2X 40 MVA Power Transformers.
    • 22 KV MV Switchgear.
    • Protection, Control, Metering & Measuring Systems.
    • Telecommunications Systems.
    • AC/DC Auxiliary System.
    • Earthing System.
    • Civil Works.